Got this from Pioneer74 over in another area and thought it could help some here, not my usual source since I have received my truck. Looking like some supply disruption again

The following items may result in a delayed build.:

(96W) Spray-in Load Box Bedliner – 4-6 week additional delay
(96L) (B5EAB)Wheel Well Liner – 4-6 weeks additional delay
(53C) (C1CAP) Max Trailer Tow – 4-6 weeks additional delay
(18S) (BLBBS) 6” ext accent running boards – 4-6 weeks additional delay - XLT or Lariat Sport extended boards.
Tonneau covers 4-6 weeks additional delay
Sponsored

 

lcrain

Well-known member
First Name
Lawson
Joined
Dec 20, 2020
Threads
4
Messages
59
Reaction score
51
Location
Dallas
Vehicles
'21 F150, '95 911 c2, '97 miata, '98 M3/4/5
Yikes. I guess my platinum with max tow and bedliner probably won’t get built March 1 as I was told.
 

YOCUBED

Well-known member
First Name
Chris
Joined
Oct 28, 2020
Threads
1
Messages
56
Reaction score
64
Location
Tuscaloosa, AL
Vehicles
2020 GLE 450, 2016 BMW M3, 2021 F150 Limited
Occupation
Emergency Physician
Eww. If I already have a build date and blend date of the 18th would this affect my order? I have the bed liner, wheel well liner and tonneau cover on my build
 

NoSnow

Well-known member
First Name
Ben
Joined
Nov 3, 2020
Threads
10
Messages
308
Reaction score
208
Location
Northern Alberta
Vehicles
F150
Occupation
Retired
Got this from Pioneer74 over in another area and thought it could help some here, not my usual source since I have received my truck. Looking like some supply disruption again

The following items may result in a delayed build.:

(96W) Spray-in Load Box Bedliner – 4-6 week additional delay
(96L) (B5EAB)Wheel Well Liner – 4-6 weeks additional delay
(53C) (C1CAP) Max Trailer Tow – 4-6 weeks additional delay
(18S) (BLBBS) 6” ext accent running boards – 4-6 weeks additional delay - XLT or Lariat Sport extended boards.
Tonneau covers 4-6 weeks additional delay
Crap. Truck is built but waiting for the box liner. 4-6 week delay - I wonder if it could just be canceled at this point
 

Sponsored

barbersbbq

Well-known member
First Name
Paul
Joined
Nov 18, 2020
Threads
8
Messages
153
Reaction score
60
Location
Augusta, GA
Vehicles
2021 F-150 Platinum
This is the last time I order anything that could’ve been done by third-party. Are you asking is for a headache
 

imgone10

Well-known member
First Name
Paul
Joined
Sep 7, 2020
Threads
8
Messages
119
Reaction score
131
Location
Boston
Vehicles
07 FJ Cruiser, 15 TRD Pro 4Runner, 2021 Lariat.
Occupation
Construction / US Army 84-96
When I ordered mine back in early October, my salesman told me to take the spray in bed liner and tonneau cover off the order, cause they always cause delays. On the spray in bed liner I have heard that they wait till they get x amount on the lot before they come in and spray them. So if the number is say 100, and your truck is the first one in that batch, it will sit till they have 100 that ordered that option.
 

Brute150

Member
Joined
Jan 17, 2021
Threads
0
Messages
19
Reaction score
20
Location
Michigan
Vehicles
FiST
Folks,
I would recommend taking this info with a grain of salt.
My Lariat with a blend date of 2/9 went into production and build was complete on 2/13.
it does have pwr running boards, spray in bed liner and wheel well liner.
Right now, my status is 'Built', waiting to get shipped to dealer.
Maybe the above delays are caused after the week of 2/13?
 

Sponsored


NoSnow

Well-known member
First Name
Ben
Joined
Nov 3, 2020
Threads
10
Messages
308
Reaction score
208
Location
Northern Alberta
Vehicles
F150
Occupation
Retired
I'm starting to think that those of us that a production date but a very long delivery date that maybe Ford has already built this delay into the ETA date. I was looking at the delivery date for a 2020 on another forum and the delivery dates for my area are typically 3 weeks(+/-) . For my 2021 the production date to my ETA is a ridiculous 7 weeks so I'm hopeful this delay is already added. If the 4-6 week is in addition then I'm going to scream.
 

NoSnow

Well-known member
First Name
Ben
Joined
Nov 3, 2020
Threads
10
Messages
308
Reaction score
208
Location
Northern Alberta
Vehicles
F150
Occupation
Retired
Folks,
I would recommend taking this info with a grain of salt.
My Lariat with a blend date of 2/9 went into production and build was complete on 2/13.
it does have pwr running boards, spray in bed liner and wheel well liner.
Right now, my status is 'Built', waiting to get shipped to dealer.
Maybe the above delays are caused after the week of 2/13?
You are one of the lucky ones. There are number of us that were built in Feb and some built in late January that have Production and ETA date but our status is "In Production". The source that Bob provided is from another forum and from what I can tell is rock solid. My guess is the delays are real but it might not be a complete shutdown that impacts everyone. It looks like you snuck through.
 

Bryan Simon

Well-known member
First Name
Bryan
Joined
Sep 16, 2020
Threads
13
Messages
1,449
Reaction score
1,096
Location
San Antonio, Texas
Vehicles
65 Ranchero, 66 ElCamino, 05 Ranger, and more
Occupation
Maintenance
The following items may result in a delayed build.:

(96W) Spray-in Load Box Bedliner – 4-6 week additional delay
(96L) (B5EAB)Wheel Well Liner – 4-6 weeks additional delay
(53C) (C1CAP) Max Trailer Tow – 4-6 weeks additional delay
(18S) (BLBBS) 6” ext accent running boards – 4-6 weeks additional delay - XLT or Lariat Sport extended boards.
Tonneau covers 4-6 weeks additional delay
This mostly looks like third party stuff.
Wonder if it is weather or possibly supply/Covid related
 

Broccoli Rob

Well-known member
First Name
Alex
Joined
Dec 21, 2020
Threads
4
Messages
247
Reaction score
143
Location
Virginia
Vehicles
2014 Ford Fusion Titanium Hybrid
Got this from Pioneer74 over in another area and thought it could help some here, not my usual source since I have received my truck. Looking like some supply disruption again

The following items may result in a delayed build.:

(96W) Spray-in Load Box Bedliner – 4-6 week additional delay
(96L) (B5EAB)Wheel Well Liner – 4-6 weeks additional delay
(53C) (C1CAP) Max Trailer Tow – 4-6 weeks additional delay
(18S) (BLBBS) 6” ext accent running boards – 4-6 weeks additional delay - XLT or Lariat Sport extended boards.
Tonneau covers 4-6 weeks additional delay

So, I know that if a truck has a blend date, it means they have all the parts reserved. Is the same true if I just have the VIN and a build week? My secondary status shows a build date of 28 February as of Thursday